Skip to page content

Channel control room · Marsden Point

Terminal & pipeline wall

15:44:02

Thu, 29 Oct · NZ time

SIMULATED telemetry around DEMO set points · not SCADA · no operational authority

Line flow

423 m³/h

Throughput

10.15 ML/d

Transfer pumps

624 kW

Parcels at jetties

52 ML

Open critical / urgent

1 / 3

Value at stake

NZ$1.42M/yr

Marsden–Wiri line flow · last 60 s

Auckland days of cover

What-if →

Amber below 7 d watch · red below 2 d minimum

Berths

  • DEMO Harbour One12 ML Jet
    Jetty 1 · Discharging 50%
  • DEMO Harbour Two20 ML Diesel
    Jetty 2 · At berth
  • DEMO Harbour Three20 ML Petrol
    Jetty 1 · Expected

Alarm & event feed

engine findings + simulated events
  • 15:35Unverified third-party excavation near Ruakākācritical
  • 15:26Transfer pump at 70% efficiency against a 78% targeturgent
  • 15:17Auckland jet cover 6.0 days, below the 7-day watch levelurgent
  • 15:08Certificate of Fitness audit evidence not attachedurgent

Tank farm

  • Jet / SAF45/120 ML · 37.5%
  • Diesel / Biofuels60/120 ML · 50%
  • Petrol65/120 ML · 54.2%
  • Government diesel reserve93/93 ML · 100%
  • Ex-refinery0/350 ML · 0%

3 tanks due API 653 internals in 18 months · 6 coating watch

Shift handover