Skip to page content
Channel × AssetStack · Marsden Point Terminal

Terminal & customer interfaces · handover evidence

Whangārei Harbour · Ruakākā · Pacific/Auckland · NZDT (UTC+13 at demo snapshot)
Terminal Command
DEMO · Synthetic operating records as at 28 October 2026. Not live telemetry, actual contracts, inspection evidence or operational authority.
4 loaded of 4 · calculations apply to loaded records
Requirements in selected pack
8
Illustrative sources, not accepted
1
Missing source records
7
DEMO-CI-H02 · No verified acceptance

Ex-refinery tank conversion · DEMO-TK-X101

17.5 ML synthetic repurposing tank. Product compatibility, outage, customer allocation and cleaning scope are unapproved; allowances do not authorise expenditure or tank release.

Illustrative source only · Asset identity snapshot
Review reference
Equipment master / DEMO snapshot
Acceptance to demonstrate
Replace the synthetic master with verified tag, drawings, materials, ownership and location data before acceptance.
Accountable reviewer
Asset data owner
Source
Equipment 6ae23fbd0022dda0580cbff0, specifications.channel_tank. Synthetic only; no accepted field evidence.
Missing source · Controlled design and as-built drawings
Review reference
Approved design and project specification
Acceptance to demonstrate
Verify asset identity, approved drawings, weld/NDT and design changes against the actual installed scope.
Accountable reviewer
Design authority
Source
Not supplied. No inspected document or accepted result is attached.
Missing source · Inspection and structural baseline
Review reference
API 653-style review; confirm applicability
Acceptance to demonstrate
Accept calibrated thickness/NDT and settlement evidence against the approved minimum thickness and settlement criteria.
Accountable reviewer
Tank integrity engineer
Source
Not supplied. No inspected document or accepted result is attached.
Missing source · Overfill and fire-system proof tests
Review reference
API 2350 / site fire-safety basis, as applicable
Acceptance to demonstrate
Retain witnessed barrier tests, setpoint checks and defect close-out against approved requirements.
Accountable reviewer
Process-safety engineer
Source
Not supplied. No inspected document or accepted result is attached.
Missing source · Cleaning, isolation and leak tests
Review reference
Approved site commissioning and isolation procedures
Acceptance to demonstrate
Confirm cleaning/gas-free evidence, permits, leak tests and signed mechanical completion before introducing product.
Accountable reviewer
Commissioning lead
Source
Not supplied. No inspected document or accepted result is attached.
Missing source · Product quality and segregation
Review reference
Customer fuel specification and approved release procedure
Acceptance to demonstrate
Accept fuel qualification, contamination controls and independent product-quality release for intended service.
Accountable reviewer
Product quality lead
Source
Not supplied. No inspected document or accepted result is attached.
Missing source · Maintenance and critical spares
Review reference
Site asset-management strategy / ISO 55001 review
Acceptance to demonstrate
Approve maintenance tasks, inspection intervals, spares applicability and procurement readiness.
Accountable reviewer
Maintenance lead
Source
Not supplied. No inspected document or accepted result is attached.
Missing source · Independent acceptance and monitoring baseline
Review reference
Approved delegation and commissioning acceptance plan
Acceptance to demonstrate
Obtain distinct accountable owner and independent approver sign-off; retain accepted baseline and post-start monitoring plan.
Accountable reviewer
Accountable asset owner
Source
Not supplied. No inspected document or accepted result is attached.
Asset reference: DEMO-TK-X101 · Snapshot: 2026-10-28 · Pack record: 6ae2416a2d7be82dac22c41c. References indicate review topics, not proof of applicability or certification.

From a DEMO checklist to governed acceptance

These public packs contain synthetic scope and missing-evidence requirements only. They are not approved handovers, audit evidence or authority to operate. Actual passports use the existing administrator workspace with distinct nominated owner and independent approver, source-linked reviews and commissioning acceptance.

Final signed acceptance creates a stored evidence snapshot and requires integration credits; these public checklists and private planning drafts do not.